Power developers seek relief for interconnection delays
Negative-57
GreyOak summary
The Electric Power Transmission Association (EPTA) urged the Ministry of Power to grant automatic financial and contractual relief to transmission developers delayed by interconnection issues. They requested deemed commercial operation dates and protection from penalties when delays are caused by separately awarded infrastructure. The association argues current frameworks expose developers to uncapped costs without tariff recovery.
What it affects
- EnergyNegative -57
Transmission developers face financial exposure due to delays.Rolling sentiment Positive +38